Trump's fast-tracking of oil pipelines hits legal roadblocks

Trump's fast-tracking of oil pipelines hits legal roadblocks

The Trump administration's effort to cut red tape and speed up major energy projects has backfired in the case of the three biggest U.S. pipelines now planned or under construction.
All three have been stalled by successful legal challenges by environmental groups alleging the administration failed to apply the regulatory scrutiny required under the law.

The Republican administration tried to accelerate permits for two multi-billion-dollar natural gas lines and jumpstart the long-stalled Keystone XL crude oil pipeline that would start in Canada. Judges halted construction on all three over the past two years, ruling that the administration granted permits without conducting adequate studies or providing enough alternatives to protect endangered species or national forests.

The delays have caused the two giant gas pipelines - Dominion Energy Inc's Atlantic Coast and EQM Midstream Partners LP's Mountain Valley - to increase their cost estimates by hundreds of millions of dollars, according to the companies. The Atlantic Coast pipeline may never be completed unless the U.S. Supreme Court overturns a lower-court decision blocking its planned route, analysts said.

Lawsuits alleging regulatory lapses are not new, but they were unsuccessful during the administration of Trump's predecessor, Democrat Barack Obama. Plaintiffs lost five separate lawsuits alleging regulatory failures during Obama's administration, according to a Reuters review of court filings for major interstate gas pipes built since 2010.

"Environmental groups definitely have been going after these pipelines more aggressively," said Amy Vazquez, Houston-based partner at the law firm of Jones Walker, who specializes in energy litigation. "It's probably because they're having a fair bit of success."

The White House declined to comment. An Energy Department spokeswoman did not comment on the litigation but said the administration remains committed to streamlining energy infrastructure development.

D.J. Gerken, senior attorney with the Southern Environmental Law Center in Asheville, North Carolina, represented the Sierra Club and other environmental groups in cases challenging the Atlantic Coast pipeline. He said the administration's rush to help industry move faster invited the legal challenges.

"Pressure from the utilities that stand to benefit from this project and the Trump administration produced flawed permits," he said.

'MYSTERIOUS' REGULATORY REVERSAL

In the case of Dominion's 600-mile (966-km) Atlantic Coast gas pipeline, from West Virginia to North Carolina, the U.S. Forest Service originally expressed skepticism about the project in 2016 when Obama was president, requesting alternative designs. But after Trump took office, the Forest Service changed course, and issued permits and a waiver for the line to cross the Appalachian Trail on national forestland in Virginia.

Petitioners including the Sierra Club, an environmental advocacy organization, sued the Forest Service, alleging the agency violated three federal acts in issuing a construction permit.

In December 2018, the U.S. Fourth Circuit Court of Appeals vacated the Forest Service decisions, with Judge Stephanie Thacker noting in her ruling that "the Forest Service's serious environmental concerns that were suddenly, and mysteriously, assuaged in time to meet a private pipeline company's deadlines."

The court said the Forest Service lacked authority to allow Dominion to build across the Appalachian Trail, which is administered by the Department of Interior. The Forest Service declined to comment.

In July, in another Atlantic Coast case brought by groups including the Sierra Club and Defenders of Wildlife, the Fourth Circuit vacated a U.S. Fish and Wildlife Service permit. Chief Judge Roger Gregory ruled that the agency, in "fast-tracking" decisions, lost sight of its mandate to protect threatened species.

The U.S. Fish and Wildlife Service declined to comment.

Atlantic Coast's original cost estimate of $6 billion to $6.5 billion has risen to $7 billion to $7.5 billion, the company said. The projected completion has shifted from late 2019 to late 2021.

The U.S. Supreme Court in October agreed to hear the Appalachian Trail case and could overrule the decision halting construction across that route.

Dominion has stopped construction on the pipe since December 2018. Spokesman Aaron Ruby said the company is confident the high court will rule in its favor and "uphold the longstanding precedent allowing pipeline crossings of the Appalachian Trail.”

RISING COSTS, LEGAL RISKS

The Fourth Circuit appeals court also stopped work on EQM’s 303-mile (488-km) Mountain Valley gas pipe from West Virginia to Virginia in June 2018, agreeing with the Sierra Club and other plaintiffs that permits issued by the Army Corps violated West Virginia rules related to stream crossings.

The state has since altered its rules, and the U.S. Army Corps of Engineers is in the process of issuing new permits for this pipeline and Atlantic Coast. But the Sierra Club is still challenging a Fish and Wildlife Service permit in a case that also is being heard by the Fourth Circuit.

EQM originally expected to complete Mountain Valley by the end of 2018 at a cost of $3.5 billion. The company said publicly that it expected the pipeline, which is mostly complete, will cost up to $5 billion and enter service in mid-2020.

Diana Charletta, chief operating officer at EQM, said that recent court decisions "have brought uncertainty and a high-level of scrutiny to the agencies’ decisions."

Officials at both Dominion and EQM dispute that approvals were fast-tracked. Dominion pointed out that it filed its application to build Atlantic Coast in 2014.

"I don't think any person can look at the regulatory review process for Atlantic Coast pipeline and say that it was fast-tracked," said Ruby, the Dominion spokesman.

EFFORT TO REVIVE KEYSTONE STALLS

TC Energy Corp's $8 billion Keystone XL pipeline, originally blocked by Obama in 2015, was revived by Trump in 2017 with the issuance of a presidential permit for the line, which would ship crude from Canada to the U.S. Gulf Coast.

Federal Judge Brian Morris in Montana blocked work on the pipe in November 2018, citing a lack of due diligence by federal regulators regarding greenhouse gas emissions and Native American land rights.

The Trump administration tried to circumvent that ruling by rescinding its original presidential permit and issuing a new one in March. That second permit now faces legal challenges from Native American groups.

TC Energy said it continues to monitor U.S. legal and regulatory issues while it plans construction. “We are committed to Keystone XL as it remains an important project for our company and for North America,” said Terry Cunha, spokesman for TC Energy.

Canadian producer Suncor Energy said in early September that the uncertain U.S. political landscape makes it unclear that the pipeline will be built. "That's one a lot of people are doing soul-searching about right now," said Suncor CEO Mark Little.
Newsletter

Related Articles

Arab Press
0:00
0:00
Close
Iranian Drone Strike on US Embassy in Saudi Arabia Reportedly Targeted Intelligence Facility
Saudi Deputy Foreign Minister Meets French Embassy Official to Strengthen Bilateral Engagement
Saudi Arabia Calls on United States to Seize Strategic Opportunity to Reshape Middle East
Dating Apps Surge in Saudi Arabia as Social Norms Rapidly Evolve Among Youth
Saudi Arabia Detains Over Fourteen Thousand Illegal Residents in Week-Long Enforcement Drive
Saudi Foreign Minister Engages in Diplomatic Talks with Pakistan, Kuwait and Latvia on Regional Developments
Saudi Arabia Intercepts Cruise Missile as Regional Tensions Intensify
Saudi Stock Market Edges Higher as Tadawul Index Records Modest Gain
Underlying Rivalry Between Saudi Arabia and UAE Persists Despite Temporary Calm
Saudi Arabia’s Non-Oil Sector Contracts in March as Regional Tensions Weigh on Business Activity
Saudi Arabia Unveils Ambition to Establish Prestigious Global Prize Rivaling the Nobel
Saudi Crown Prince to Engage Wall Street in Push for Investment and Economic Expansion
Iran Accuses Saudi Arabia and UAE After Downing of Chinese-Made Drone
Saudi Arabia Condemns Attack on Hospital in Sudan, Calls for Protection of Civilians
Coordinated Drone Strike Targets CIA Facility Within US Embassy in Saudi Arabia
Italy’s Meloni Prioritises Energy Security and Strait of Hormuz Stability During Gulf Tour
Uncertainty Emerges Over Timeline and Direction of Saudi Arabia’s Ambitious Ski Resort Project
UAE and Saudi Arabia Escalate Strategy with Drone Operations Targeting Iran
Trump Delivers Characteristic Remarks on Saudi Crown Prince Amid Intensifying Iran Conflict
Drone Strike on US Embassy in Riyadh Caused Greater Damage Than First Reported
Saudi Arabia Introduces Flexible Solutions for Expired Visas Amid Regional Disruptions
Saudi Arabia’s Online Car Market Accelerates with AI Pricing and Fully Digital Buying Experience
Saudi Arabia Reassesses Defence Strategy as Iranian Drone Threat Drives Shift in Military Partnerships
Drone Strikes Target Saudi Arabia, Kuwait and Bahrain as Regional Conflict Intensifies
Japan and Saudi Arabia Align Efforts to Ease Rising Tensions with Iran
Saudi Crown Prince and Italy’s Meloni Strengthen Strategic Ties in High-Level Talks
SpaceX Explores Potential Five Billion Dollar Investment from Saudi Sovereign Wealth Fund Ahead of IPO
Saudi Arabia Lifts Key Import Barriers to Expand Access for U.S. Beef Exports
Saudi Arabia Enforces Strict Travel Penalties for Visits to Restricted Countries
Italy’s Meloni Embarks on Strategic Gulf Tour to Address Energy Security and Regional Stability
Saudi Film Festival Rescheduled to Summer as Regional Tensions Continue
Saudi Arabia Reports Forty Two Point Six Billion Dollars in Foreign Tourist Spending in 2025
Saudi Crown Prince and Russian President Hold Strategic Call on Escalating Regional Crisis
Saudi Arabia Advances Rail Network as Strategic Alternative to Strait of Hormuz Shipping Route
Ruanyun Edai Launches Saudi Arabia Hub With Forecast of Ten Percent Revenue Growth
Greek Defence Minister Visits Troops in Saudi Arabia Following Successful Missile Interception
Saudi Arabia Expands Global Strategy With Focus on African Critical Minerals
SpaceX Explores Potential Five Billion Dollar Investment From Saudi Fund Ahead of Possible IPO
US Central Command Dismisses Iranian Claim of Mass Casualties Among American Personnel in Saudi Arabia
Co-Diagnostics to Establish Molecular Diagnostics Facility in Saudi Arabia Through Joint Venture
Trump Engages Saudi Crown Prince in Talks on Potential Iran Ceasefire
Saudi Arabia’s Sadara Suspends Operations as Supply Chain Disruptions Intensify
Saudi Arabia Accelerates Energy Shift by Trading Oil Revenues for Battery Investments
Saudi Arabia Introduces Flexible Options for Expired Visas Amid Regional Disruptions
Online Narratives Surge as Iran–US Tensions Spill Into Digital Arena Following Trump Remarks
Saudi Arabia Urges Trump to Seize Strategic Moment as UAE Weighs Ground Deployment
Saudi Arabia Redirects Nearly One Million Barrels of Oil Daily Away from Strait of Hormuz
Saudi Arabia Carries Out Execution of Businessman Linked to 2011 Qatif Unrest
Ukraine–Saudi Defense Pact Signals Rising Demand for Battlefield Expertise
Saudi Arabia Balances Diplomacy and Defense Preparedness Amid Iran Conflict
×